Allied Material tungsten reduction and carburisation facilities
富山製作所から約1kmの場所
prj-jp-almt-tungsten
What does the record establish?
METI's certified-plan list does not state a location. The recipient's 9 April 2026 release identifies a new site about 1 km from Toyama Works. Site secured does not establish construction commencement, ownership of the land, or operation.
Financial standing
1 directly linked instruments. Recorded financial states: Decided. A commitment, a payment and a project cost remain separate.
Inspect instruments and termsLegal and policy context
1 parent policy records; 1 project designations. Designation confers standing, not finance. Material and stage overlaps with controls do not establish a restriction on this project.
Read the policy recordsIndustrial evidence
No source-reviewed project milestone is published in this corpus. Financing records may still contain attributed activity reports; this gap does not establish inactivity.
See evidence gapsFinancial evidence and chronology
Each instrument keeps its own financial history. These dates describe financial states, not construction or production. Amounts are the current recorded terms, not historical amounts at every date below.
Grant · Japan Organization for Metals and Energy Security (JOGMEC)※助成額は約75億円 · Decided · Commitment
- Provider organizations
- Japan Organization for Metals and Energy Security (JOGMEC)
- Recipient
- 株式会社アライドマテリアルAllied Material Corporation
- Legal authority as stated
- 経済安全保障推進法 (Economic Security Promotion Act)
· Announced
METI's list gives the subsidy with the plan certified on 令和8年3月18日.
経済産業省 (Ministry of Economy, Trade and Industry, Japan)Exact status date not stated · Decided
Listed among JOGMEC's grant decisions (交付決定事業) for 令和7年度; the decision date is not stated.
独立行政法人エネルギー・金属鉱物資源機構 (JOGMEC)
Source-stated terms
- 申請者負担額の1/2を上限 独立行政法人エネルギー・金属鉱物資源機構 (JOGMEC)
Programme-wide maximum grant rate, as stated in JOGMEC's 助成率 table. It is not an exact subsidy-to-total-project-cost ratio for this plan.
The amount is approximate as both lists print it (約, "about"); the yen figure is 億円 × 100,000,000. Lifecycle review on 3 October 2026 retains decided status and an unknown grant-decision date. The 9 April recipient release adds an announced physical project near Toyama Works and a first-half FY2028 operating target. Its approximately JPY 15.9 billion investment plan is separate from the approximately JPY 7.5 billion public grant. The reviewed sources do not establish grant cash receipt, construction commencement or operation.
Full financial instrument, conditions and field-level evidenceCapital stack
One layer per value role. Only committed public money, and joint-vehicle money apart from it, is summed, per currency; everything else is listed. There is no total across layers.
Public commitments
1 row · summed per currencyCommitted to a recipient by a government or public enterprise, at the status each row states. A contracted, partially disbursed or disbursed row is binding because an agreement is executed; payment is tracked separately by status. A contracted row need not mean funds are obligated or paid, and a partially disbursed row is not fully paid. Summed per currency and per instrument, never across either; a part is never added to its package.
JPY
Grant1 row
Not yet binding
- Approximately
- 7.5 billion
1 counted
Source-reviewed industrial observations
No source-reviewed project milestone is published for this undertaking. Any financing-row activity reports below remain attributed observations, not independently reviewed project milestones. Missing evidence does not establish inactivity.
Policy context
These records directly parent the project's finance or designation entries. Their presence does not establish a causal effect on industrial activity.
18 Mar 2026 · Active
Certification of Allied Material's critical-minerals supply-assurance plan for tungsten under the Economic Security Promotion Act
METI / JOGMEC
Designations
Recognition under a scheme confers standing, not money, and is never counted as capital.
18 Mar 2026
タングステンの還元及び炭化設備を新設し、タングステン粉末及び炭化タングステン粉末の生産能力を向上させる。
Certified supply-assurance plans for critical minerals (Economic Security Promotion Act) · 2025重要鉱物第2号-1
· Processing
Control clauses on the same materials and stages
Clauses whose covered items share a material and a supply-chain stage with this project, with their legal status on 3 Nov 2026. An overlap of items, not a finding that the project is affected.
Record
- Sponsors
- Allied Material CorporationCompany
- Location
- 富山製作所から約1kmの場所JP
- Stages
- Processing
- Materials
- TungstenTracked materials only
- Latest financing-row activity report
- Announced9 Apr 2026株式会社アライドマテリアル (A.L.M.T. Corp.)
What remains unknown
Gaps describe the available SMPT record. They do not establish that an activity did not occur.
- No project-native source-reviewed industrial milestone is published. Attributed activity in financing histories remains a separate evidence class; no exact milestone date or facility-wide conclusion is inferred.
- Historical amount review is incomplete. Current amounts cannot be read as a time series of earlier commitments.
- Structural links and shared materials do not demonstrate that a government measure caused an industrial outcome.
Evidence
Every project fact names the source that states it.
経済産業省 (Ministry of Economy, Trade and Industry, Japan)
- Fields supported
- Name · Sponsors · Materials
- Evidence level
- Explicit
- Location in document
- Section 4, plan 2025重要鉱物第2号-1
- Qualification
- "タングステンの還元及び炭化設備を新設し、タングステン粉末及び炭化タングステン粉末の生産能力を向上させる。"
経済産業省 (Ministry of Economy, Trade and Industry, Japan)
- Fields supported
- Supply-chain stages
- Evidence level
- Ambiguous
- Location in document
- Section 4, plan 2025重要鉱物第2号-1
- Qualification
- 還元及び炭化 (reduction and carburisation) into tungsten and tungsten carbide powder is read as processing.
タングステンの供給能力を約1.5倍に増強 総額約159億円を投資、2028年度上期稼働へ
株式会社アライドマテリアル (A.L.M.T. Corp.)
- Fields supported
- Location
- Evidence level
- Explicit
- Location in document
- Page 1, new-site paragraph
- Qualification
- A site of approximately 40,000 square metres was secured about 1 km from the recipient's Toyama Works for the new powder plant.
| Source | Fields supported | Evidence level | Location |
|---|---|---|---|
| 重要鉱物(経済安全保障推進法に基づく認定供給確保計画) 経済産業省 (Ministry of Economy, Trade and Industry, Japan) · Source dossier |
| Explicit "タングステンの還元及び炭化設備を新設し、タングステン粉末及び炭化タングステン粉末の生産能力を向上させる。" | Section 4, plan 2025重要鉱物第2号-1 |
| 重要鉱物(経済安全保障推進法に基づく認定供給確保計画) 経済産業省 (Ministry of Economy, Trade and Industry, Japan) · Source dossier |
| Ambiguous 還元及び炭化 (reduction and carburisation) into tungsten and tungsten carbide powder is read as processing. | Section 4, plan 2025重要鉱物第2号-1 |
| タングステンの供給能力を約1.5倍に増強 総額約159億円を投資、2028年度上期稼働へ 株式会社アライドマテリアル (A.L.M.T. Corp.) · Source dossier |
| Explicit A site of approximately 40,000 square metres was secured about 1 km from the recipient's Toyama Works for the new powder plant. | Page 1, new-site paragraph |
For citations, open a parent policy record for BibTeX, RIS and CSL formats. Cite original documents for claims about government action.
Project registry JSON with sources · Full dataset and download guide