Ioneer Rhyolite Ridge LLC
Rhyolite Ridge on-site lithium processing facility
fin-us-doe-rhyolite-ridge-guarantee-2025
Reading this record
What the evidence says — and does not say
- What kind of figure?
- CommitmentMoney, or a money-like promise, committed to a named recipient or project. The only role ever summed.
- What has happened legally?
- ContractedA binding agreement has been executed. Not a payment, and not necessarily an obligation of funds: an agreement can leave that to a later step.
- Has money been paid?
- Follow the payment evidenceThis status does not itself establish a cash payment. In particular, a signed contract does not necessarily establish an obligation of funds.
- What does it link to?
- Project attributionOne registered project is linked directly to this row. The link alone does not prove the amount was paid or that the project advanced.
This is a commitment role, but the financial status still determines legal standing and payment. Funding and verified industrial outcomes remain separate. A financial record alone never independently verifies construction, commissioning or production. Read SMPT's counting and evidence rules.
Amount
As stated “$996 million loan guarantee ($968 million principal plus $28 million capitalized interest)”
USD 996,000,000 · Exact · Currency stated in the source
Record
- Provider
- U.S. Department of Energy, Advanced Technology Vehicles Manufacturing Loan ProgramU.S. Department of EnergyGovernment body
- Legal authority
- Energy Independence and Security Act of 2007, Section 136 — Advanced Technology Vehicles Manufacturing Loan Program
- Programme
- None named
- Recipient
- Ioneer Rhyolite Ridge LLCIoneer Rhyolite Ridge LLCCompany
- Project
- Rhyolite Ridge on-site lithium processing facilityRhyolite Ridge on-site lithium processing facilities capital stack →
- Facility
- On-site lithium carbonate processing facility and associated infrastructure
- Location
- Esmeralda County, NevadaUS
- Stages
- ProcessingSingle stage
- Materials
- LithiumTracked materials only
Status
Financial and physical progress are separate histories. The last entry is current.
Financial
- Contractedcurrent
DOE's 17 January 2025 announcement expressly reports closing the $996M ATVM loan guarantee to Ioneer Rhyolite Ridge LLC. Funding is subject to conditions precedent; no positive advance evidence in reviewed June–August 2026 issuer filings. The 2023 conditional loan is not a second count.
Implementation
- Feasibilitycurrent
The 30 July 2026 issuer report confirms June-quarter pre-construction engineering and feasibility studies with strategic partner, final investment decision and physical construction still pending. Stage is observed by this source date; no exact phase transition date is claimed.
Ioneer Ltd / U.S. Securities and Exchange Commission (EDGAR)
Notes
ONE closed ATVM loan guarantee: $996M total = $968M principal + $28M capitalized interest; neither component is a second amount. January 2023 conditional commitment was revised and replaced at closing, not additive. As of latest reviewed issuer disclosures (June-quarter activities July 30, half-year accounts August 13, 2026), no primary source positively establishes a first federal advance; preserve contracted, do not classify as partially disbursed or assert conclusively that no draw has ever happened. Reported $4.273M establishment fees are costs paid by Ioneer, NOT DOE disbursement. First draw conditions include strategic partner equity, additional funds and revised financial model. Sibanye-Stillwater did not proceed with proposed project equity in February 2025; 2026 KIND/Hyundai understandings remained nonbinding. DOE's early NEPA summary names proposed Rhyolite Ridge Holdings LLC but the 17 Jan 2025 closing names Ioneer Rhyolite Ridge LLC; these are not assumed equivalent. Processing facilities only: federal guarantee does not finance open-pit mine construction or separately fund the untracked boron co-product, and permits and feasibility are not physical construction.
Evidence
Every populated field names the source that states it, how directly, and where.
DOE closes $996 million loan guarantee for Ioneer Rhyolite Ridge
U.S. Department of Energy, Loan Programs Office
- Fields supported
- Instrument · Value role · Capital source · Amount · Provider · Legal authority · Recipient · Project · Facility · Location · Supply-chain stages · Materials · Status
- Evidence level
- Explicit
- Location in document
- DOE closing release, 17 January 2025, paragraphs 1–2 and ATVM programme description
- Qualification
- Federal agency establishes a closed $996M guarantee and borrower, not disbursement; amount splits $968M principal and $28M capitalized interest.
Ioneer January 2025 SEC exhibit — $996 million DOE loan closing
Ioneer Ltd / U.S. Securities and Exchange Commission (EDGAR)
- Fields supported
- Instrument · Amount · Recipient · Status
- Evidence level
- Explicit
- Location in document
- Issuer's 17 January 2025 loan-closing statement and conditional-loan comparison
- Qualification
- Confirms closed instrument, amount and 2023 increase; earlier conditional commitment not additive.
DOE/EIS-0565 — Rhyolite Ridge mine processing loan scope
U.S. Department of Energy, NEPA
- Fields supported
- Project · Facility · Location · Supply-chain stages · Materials
- Evidence level
- Explicit
- Location in document
- DOE/EIS-0565 Summary, loan-only processing scope
- Qualification
- Excludes development/operation of open-pit mine. NEPA references a different proposed borrower, so it does not support recipient organization assignment.
Ioneer Transition Form 20-F (2026) — Rhyolite Ridge financing conditions and pre-FID status
Ioneer Ltd / U.S. Securities and Exchange Commission (EDGAR)
- Fields supported
- Status
- Evidence level
- Explicit
- Location in document
- DOE Loan discussion; conditions precedent to first advance and FID financing requirements
- Qualification
- Issuer says draw conditions include equity partner, additional capital and revised financial model; no first advance evidenced.
Ioneer 30 July 2026 Quarterly Activities Report — Rhyolite Ridge remains pre-FID
Ioneer Ltd / U.S. Securities and Exchange Commission (EDGAR)
- Fields supported
- Project · Supply-chain stages · Materials · Status
- Evidence level
- Explicit
- Location in document
- July 2026 Quarterly Activities Report, strategic partnering, timeline and ASX LR 5.3.2
- Qualification
- FID awaited, future construction milestone; zero production/development activity in June 2026 quarter. A non-binding Korean partnership MOU is not a draw or construction.
Ioneer half-year financial statements ended June 30, 2026 (SEC Exhibit 99.1)
Ioneer Ltd / U.S. Securities and Exchange Commission (EDGAR)
- Fields supported
- Status
- Evidence level
- Explicit
- Location in document
- Note 10 unamortized loan fees; Note 9 pre-FID exploration/development classification; directors' compliance statement
- Qualification
- Loan fees are not cash from DOE; amortization begins after first draw and financial statements still pre-FID. No guarantee disbursement affirmed.
| Source | Fields supported | Evidence level | Location |
|---|---|---|---|
| DOE closes $996 million loan guarantee for Ioneer Rhyolite Ridge U.S. Department of Energy, Loan Programs Office · Source dossier |
| Explicit Federal agency establishes a closed $996M guarantee and borrower, not disbursement; amount splits $968M principal and $28M capitalized interest. | DOE closing release, 17 January 2025, paragraphs 1–2 and ATVM programme description |
| Ioneer January 2025 SEC exhibit — $996 million DOE loan closing Ioneer Ltd / U.S. Securities and Exchange Commission (EDGAR) · Source dossier |
| Explicit Confirms closed instrument, amount and 2023 increase; earlier conditional commitment not additive. | Issuer's 17 January 2025 loan-closing statement and conditional-loan comparison |
| DOE/EIS-0565 — Rhyolite Ridge mine processing loan scope U.S. Department of Energy, NEPA · Source dossier |
| Explicit Excludes development/operation of open-pit mine. NEPA references a different proposed borrower, so it does not support recipient organization assignment. | DOE/EIS-0565 Summary, loan-only processing scope |
| Ioneer Transition Form 20-F (2026) — Rhyolite Ridge financing conditions and pre-FID status Ioneer Ltd / U.S. Securities and Exchange Commission (EDGAR) · Source dossier |
| Explicit Issuer says draw conditions include equity partner, additional capital and revised financial model; no first advance evidenced. | DOE Loan discussion; conditions precedent to first advance and FID financing requirements |
| Ioneer 30 July 2026 Quarterly Activities Report — Rhyolite Ridge remains pre-FID Ioneer Ltd / U.S. Securities and Exchange Commission (EDGAR) · Source dossier |
| Explicit FID awaited, future construction milestone; zero production/development activity in June 2026 quarter. A non-binding Korean partnership MOU is not a draw or construction. | July 2026 Quarterly Activities Report, strategic partnering, timeline and ASX LR 5.3.2 |
| Ioneer half-year financial statements ended June 30, 2026 (SEC Exhibit 99.1) Ioneer Ltd / U.S. Securities and Exchange Commission (EDGAR) · Source dossier |
| Explicit Loan fees are not cash from DOE; amortization begins after first draw and financial statements still pre-FID. No guarantee disbursement affirmed. | Note 10 unamortized loan fees; Note 9 pre-FID exploration/development classification; directors' compliance statement |