CACanadaGovernment of Canada

Nouveau Monde Graphite

Matawinie Mine

CommitmentOfftakePublicContracted

fin-ca-g7-2025-nmg-offtake

Reading this record

What the evidence says — and does not say

What kind of figure?
CommitmentMoney, or a money-like promise, committed to a named recipient or project. The only role ever summed.
What has happened legally?
ContractedA binding agreement has been executed. Not a payment, and not necessarily an obligation of funds: an agreement can leave that to a later step.
Has money been paid?
Follow the payment evidenceThis status does not itself establish a cash payment. In particular, a signed contract does not necessarily establish an obligation of funds.
What does it link to?
Project attributionOne registered project is linked directly to this row. The link alone does not prove the amount was paid or that the project advanced.

This is a commitment role, but the financial status still determines legal standing and payment. Funding and verified industrial outcomes remain separate. A financial record alone never independently verifies construction, commissioning or production. Read SMPT's counting and evidence rules.

Amount

No amount is stated for this instrument. Its terms below are what the source commits to; no value is estimated.

Record

Provider
Government of CanadaGovernment of CanadaGovernment body
Legal authority
Not stated
Programme
None named
Recipient
Nouveau Monde GraphiteNouveau Monde GraphiteCompany
Project
Matawinie MineMatawinie Mine capital stack →
Facility
Not stated
Location
Not stated
Stages
MiningSingle stage
Materials
GraphiteTracked materials only

Status

Financial and physical progress are separate histories. The last entry is current.

Financial

  1. Announced

    "offtake arrangements with the Government of Canada, Panasonic (Japan), and Traxys (Luxembourg)"

    Natural Resources Canada

  2. Contractedcurrent

    NMG reports signing the definitive binding offtake and marketing agreements with Canada. No payment or delivery is evidenced by signing.

    Nouveau Monde Graphite / SEC

Implementation

  1. Constructioncurrent

    NMG dates the start of Phase 2 Matawinie Mine construction to April 13, 2026 and reports ongoing civil works. This physical milestone is separate from the May 15 FID and May 19 ceremony; it does not state production or financing disbursement.

    Nouveau Monde Graphite / SEC

Terms

Operative terms as the source words them.

TermFigureAs stated
Quantity covenant30,000 tonnes per annum“30,000 tonnes per annum”Graphite concentrate from the Phase 2 Matawinie Mine under the definitive agreement.Nouveau Monde Graphite / SEC
Duration7 years“seven-year period as of the start of commercial production”The term begins at the start of commercial production, not the agreement signing date; no calendar end date is inferred.Nouveau Monde Graphite / SEC

Notes

Definitive binding Government of Canada offtake signed May 13, 2026 for 30,000 tonnes per annum over seven years from commercial production. Take-or-pay at a fixed North American market price with an upside-sharing resale mechanism; no numeric price is disclosed. No payment or shipment is inferred. The Panasonic and Traxys offtakes are private and the Government of Japan investment intention is not a commitment; none is recorded as a row.

Evidence

Every populated field names the source that states it, how directly, and where.

  1. Backgrounder: Canada unlocks 26 new investments and partnerships with 9 allied countries to secure critical minerals supply chains

    Natural Resources Canada

    Fields supported
    Instrument · Value role · Capital source · Provider · Recipient · Status · Project · Materials · Supply-chain stages
    Evidence level
    Explicit
    Location in document
    First paragraph of the list
    View source dossier →
  2. NMG Announces Results of its Annual General and Special Meeting of Shareholders and Signature of a Definitive Binding Offtake Agreement with the Government of Canada

    Nouveau Monde Graphite / SEC

    Fields supported
    Instrument · Provider · Recipient · Project · Materials · Supply-chain stages · Status · Terms
    Evidence level
    Explicit
    Location in document
    Government of Canada Offtake Agreement
    Qualification
    NMG reports the definitive binding agreement signed May 13, 2026, its annual volume, take-or-pay structure and seven-year term beginning with commercial production.
    View source dossier →
  3. Management Discussion & Analysis for the six-month period ended June 30, 2026

    Nouveau Monde Graphite / SEC

    Fields supported
    Project · Status
    Evidence level
    Explicit
    Location in document
    Matawinie Mine Project (Phase 2), pages 9–10
    Qualification
    NMG reports construction began April 13, 2026. Applies to the Phase 2 mine only; demonstration-plant activity and the separately financed Bécancour plant are not mine commercial operation.
    View source dossier →